Phase 1 Complete

Phase 1 Complete

The 1st phase of the refurbishment is now complete and we have reopened, (although still observing Covid-19 advice.) Phase 1 has seen many changes to the village hall including new windows, a new boiler installed and photovoltaic cells on the roof, this along with new...
First Site Meeting

First Site Meeting

The first site meeting was held at the hall today, Thursday 8th April with Pete, Marcus and Sue representing the Village Hall Committee, Michael the Architect and Peter and Paul from HBC builders. Great progress has been made and all is on track. Harbour View has been...
And so it begins!

And so it begins!

Wednesday 24 March 2021 was a big day in the village of Combwich. It saw the start of the biggest refurb that the Village Hall has seen for decades. The sun shone down on village volunteers who joined forces and began to clear the hall ready for the trades to move in...
Almost there!

Almost there!

We are almost ready to start the refurbishment.  So far we have secured a total of £211,400 thanks to Hinkley Community Fund, Somerset County Council Carbon Reduction Scheme, Otterhampton Parish Council and the Garfield Weston Foundation.  We are now waiting...
Refurb Update

Refurb Update

We have had a slight delay with the submission of the grant application and the Business Plan to the OPPT Committee, Parish Council and then the EDF Community Fund. The application should be submitted very soon. We may have an issue with the installation of an...